Originally Posted by
alpha
v0.7 - Fixed the comma problem and made quite a lot of changes which will make adding new OGR or RC5 projects trivial. Also some other small miscellaneous changes.
Hi alpha,
one minor Problem. I think the counting of working days ist not correct
for ogrng because there no different logfiles (like for ogrp2); all ogr26 and
ogr27 logging goes into files like "pproxyogrngYYYYMMDD". But pppla counts
all logfiles with "ogrng" in it.
For example after 2 days for my little proxy
Code:
Overall OGR-27 PProxy stats based on 121 days:
Smallest: 55.80 Gnodes, submitted on 26/02/2009
Largest: 615.77 Gnodes, submitted on 25/02/2009
Average: 279.05 Gnodes
Total: 17,580 Gnodes
Rate: 145 Gnodes/day, 0.00 Gnodes/sec, 1 stubs/day
Best days: 11,952 Gnodes, on 26/02/2009
49 stubs, on 26/02/2009
Stubs done: 63 (0.00032% of project)
Sure, the % of Project is also wrong until we get numbers from dnet.
Bye,
clzupp